Drivers in Sparks face lane closures and detours on two major roads as the Regional Transportation Commission of Washoe County (RTC) continues construction on Prater Way and Sparks Boulevard.

The RTC's Nov. 20 traffic report details traffic impacts on both corridors, with Sparks Boulevard work anticipated to last through June 2027. The report also includes updates on two other projects in the area.

Prater Way paving nears final stage

Crews have completed bottom-lift paving on Prater Way, according to RTC project manager Kimberly Diegle. Preparations are underway for the final paving lift, which will be placed when weather allows.

Two-way traffic is being maintained on the north side of Prater Way. No street parking is allowed between Pyramid Way and Standford Way. Sixth and Seventh streets are closed at Prater Way, with access off Wright Way. The free right turn from northbound Pyramid Way to eastbound Prater Way is also closed.

Side streets and commercial driveways remain accessible using temporary ramps, except during brief periods when construction equipment is active.

Sparks Boulevard work runs through June 2027

The Sparks Boulevard project stretches from the I-80 westbound ramp intersection to the Shadow Lane intersection. Construction is anticipated to continue through June 2027, according to RTC project manager Garrett Rodgers.

The report lists around-the-clock single-lane closures in both directions. Northbound, the closure runs between Prater Way and Baring Boulevard. Southbound, it runs between Baring Boulevard and Prater Way. Daily single-lane closures also affect both directions between Lincoln Way/Prater Way and Baring Boulevard/Shadow Lane.

Howard Drive is closed at Sparks Boulevard. Drivers should use Fargo Way and O'Callaghan Drive as a detour.

Northbound construction hours run 5 a.m. to 2 p.m. Monday through Friday. Southbound hours are 9 a.m. to 7 p.m. Monday through Friday. Nighttime work may also occur.

Residents can get updates through the Sparks Boulevard project website or by texting SPARKS to 866-540-8466.

Other project updates

The Sparks Boulevard/Ion Drive traffic signal project is substantially complete, according to RTC project manager LaShonn Ford. Intermittent closures may still occur as crews finish final items.

The Sun Valley Boulevard corridor improvements project remains in final design, with construction anticipated to start in fall 2027. The project extends from Scottsdale Road to Seventh Avenue. Sierra Nevada Construction is on site through November 2026 to complete subsurface utility engineering as part of design efforts, according to RTC project manager Jessica Dover. No work is scheduled the week of Nov. 23, and roadway closures are not anticipated as part of the exploratory work.

The Sparks Boulevard project's June 2027 anticipated completion date is the longest timeline among the active projects listed in the report.