Sparks Boulevard drivers face anticipated round-the-clock single-lane closures in both directions. The Regional Transportation Commission (RTC) of Washoe County expects the construction to continue through June 2027.

The project runs from the Sparks Boulevard/I-80 westbound ramp intersection to the Sparks Boulevard/Shadow Lane intersection, according to the RTC's Friday, Nov. 13, traffic report.

What drivers should expect

As of the week of Friday, Nov. 13, the RTC anticipated these closures:

  • A 24/7 single-lane closure on northbound Sparks Boulevard between Lincoln Way and the Baring Boulevard intersection.
  • A 24/7 single-lane closure on southbound Sparks Boulevard between Baring Boulevard and Prater Way.
  • Howard Drive closed at Sparks Boulevard. The RTC advises drivers to use Fargo Way and O'Callaghan Drive as a detour.
  • Daily single-lane closures in both directions on Sparks Boulevard between Lincoln Way/Prater Way and Baring Boulevard/Shadow Lane.

Northbound construction generally occurs from 5 a.m. to 2 p.m., Monday through Friday. Southbound work runs from 9 a.m. to 7 p.m., Monday through Friday. Nighttime work and work during special events may also occur, the RTC said.

Garrett Rodgers, RTC project manager, said in a Nov. 2 announcement that the agency looks "forward to completing this project on schedule in June 2027."

New traffic signal active at Ion Drive

A separate project at Sparks Boulevard and Ion Drive is substantially complete. The signal is now active. Intermittent closures may still occur as crews finish final items, according to the RTC. RTC project manager LaShonn Ford is overseeing that work.

Sun Valley Boulevard work ahead

On Sun Valley Boulevard, the RTC's corridor improvement project is in its final design phase. Construction is anticipated to start in fall 2027. The project limits extend from Scottsdale Road to Seventh Avenue.

Sierra Nevada Construction will be on site through November 2026 to complete subsurface utility engineering as part of final design efforts, the RTC said. During the week of Monday, Nov. 16, through Friday, Nov. 20, that work will occur during the day on side streets throughout the project limits. Roadway closures are not anticipated as part of this exploratory work, according to the RTC. RTC project manager Jessica Dover is overseeing the Sun Valley project.

Residents can follow the Sparks Boulevard project at sparksblvdproject.com or text "Sparks" to 866-540-8466 for updates.